25
submitted 7 months ago by eleitl@lemmy.ml to c/collapse@lemmy.ml
you are viewing a single comment's thread
view the rest of the comments
[-] zifnab25@hexbear.net 9 points 7 months ago

In Georgia, demand for industrial power is surging to record highs, with the projection of electricity use for the next decade now 17 times what it was only recently.

The first new nuclear plants since Three Mile Island just came online in Georgia last year. Vogtle 3 and 4 will produce a combined 1.2 GWe at peak capacity.

These reactors took 16 years and multiple bailouts and bankruptcies to complete, costing an estimated $34B to finish.

Hopefully, future power construction will move a little smoother.

As a comparison, the Taishan Nuclear Power Plant took ten years to complete at the cost of around $7.5B and it has a peak generation of 3.3 GWe

[-] huf@hexbear.net 3 points 7 months ago

4.5x freedom markup. not even that high.

this post was submitted on 07 Mar 2024
25 points (96.3% liked)

Collapse

3237 readers
2 users here now

We have moved to https://lemm.ee/c/collapse -- please adjust your subscriptions

This is the place for discussing the potential collapse of modern civilization and the environment.


Collapse, in this context, refers to the significant loss of an established level or complexity towards a much simpler state. It can occur differently within many areas, orderly or chaotically, and be willing or unwilling. It does not necessarily imply human extinction or a singular, global event. Although, the longer the duration, the more it resembles a ‘decline’ instead of collapse.


RULES

1 - Remember the human

2 - Link posts should come from a reputable source

3 - All opinions are allowed but discussion must be in good faith.

4 - No low effort posts.


Related lemmys:

founded 4 years ago
MODERATORS